THE BORE HOLE DRILLING 1.1
SITE OFFICE AND SITE STORE CONSTRUCTION. 1.2
FORMWORK TO FOUNDATION AND POOL ACCESSORIES ROUGH INSTALLATION
WIRE MESH, DPM, ROUGH INS PLUMBING, AND FORMWORK TO PERIMETER OF FOUNDATION
SLAB TO FIRST FLOOR AND BEAM REINFORCEMENT
FIRST FLOOR SLAB
LINTEL FORMWORK
Thursday 15 August 2013
Introduction
For the next few six months I will be updating you all with the daily construction works, challenges, the expected and unexpected that we will encounter in the construction of my first residential building project ( a contemporary residential home). Take a look at the 3D model below.
I welcome new ideas and suggestions for the better looks and stability of the building. Details drawings will be uploaded soon, as we are still on the design stage of the project. Stay tight.
Yours host
Mike Obi C. Aka MOC
Subscribe to:
Posts (Atom)